On this, March 26, 2021, Mr. Teodor Osikovski, Manager and Owner of KMC LTD, signed the contract with Bulgartransgaz EAD with subject: Design, implementation and commissioning of the construction of “Electric substation 110 / 6kV, compressor station “Valchi Dol””.
The works include a complete replacement of the existing complete distribution system 6 kV, installation of new synchronous motors exciters, replacement of power cables, as well as rehabilitation of the building.